Conversion of Dahlem wastewater treatment plant during ongoing operation

structure-square

Smaller wastewater treatment plants are often designed as single-line activated sludge plants. The decommissioning concept is therefore of particular importance when conversion work is required. The Dahlem wastewater treatment plant with a capacity of 4,700 population equivalents also posed special challenges in this regard.

Decommissioning concept

Together with the operator and the responsible authority, a period of time was defined on the basis of the operating data during which the plant could be taken out of operation without having to use a costly mobile temporary biology system. Decisive factors here were the average dry weather inflow and existing buffer volumes of upstream structures.

As the aeration tank had not been completely emptied for many years, it was first emptied in advance. This allowed deposits and blockages to be removed and the structural condition of the tank to be checked at the same time.

Scheduled construction process in 3 days

Thanks to the early and detailed planning of all work steps, the entire decommissioning process, including emptying the basin, was reduced to less than three days. The construction process went smoothly and according to plan.

Source: Pictures / Text by Sven Dichter

Further contributions

News from BITControl

Our new company brochure is here!
Three areas of expertise. One shared goal. Process engineering, specialist planning and software work together seamlessly at BITControl. This results in bespoke solutions for water, [...]
Lunch together by the lake and in the garden
In April, we were treated to a very special lunch: the Maximinschule – a special school for learning and language – [...]
BITControl is a FlowChief partner
BITControl FlowChief has been a Silver Certified Partner since February 2026. Service is the be-all and end-all. Service is our top priority [...]