Smaller wastewater treatment plants are often designed as single-line activated sludge plants. The decommissioning concept is therefore of particular importance when conversion work is required. The Dahlem wastewater treatment plant with a capacity of 4,700 population equivalents also posed special challenges in this regard.
Decommissioning concept
Together with the operator and the responsible authority, a period of time was defined on the basis of the operating data during which the plant could be taken out of operation without having to use a costly mobile temporary biology system. Decisive factors here were the average dry weather inflow and existing buffer volumes of upstream structures.
As the aeration tank had not been completely emptied for many years, it was first emptied in advance. This allowed deposits and blockages to be removed and the structural condition of the tank to be checked at the same time.
Scheduled construction process in 3 days
Thanks to the early and detailed planning of all work steps, the entire decommissioning process, including emptying the basin, was reduced to less than three days. The construction process went smoothly and according to plan.





Source: Pictures / Text by Sven Dichter