30.04.2019

Optimisation of the sludge cycle

structure-square

Improving the purification performance of the Zahmen wastewater treatment plant

Since its construction, the Zahmen wastewater treatment plant in the municipality of Grebenhain has had problems with the function of the secondary clarifier. Here, the sludge level rose significantly to critical levels when the mixed water inflow began and continued.

The wastewater treatment plant was analysed, recalculated and evaluated by BITControl. The following measures were implemented to improve the treatment performance:

  • A new, larger inlet cylinder with inlet pipe was installed in the secondary clarifier
  • A partition wall was installed in the RLS shaft in order to be able to control the two secondary clarifiers separately. A bypass pipe was also installed to improve the operating point of the pumps.
  • At the same time, parts of the EI&C technology were renewed or supplemented: switchgear, sludge level measurement, automation technology
    The return sludge control was converted to sludge level control.
Further contributions

News from BITControl

Fine adjustment of the aeration control: more nitrogen elimination, less energy consumption
Replacing the aerators at the wastewater treatment plant Au The best aerators and blowers and the best control tools are useless if the [...]
We are hiring: IT Specialist Application Development (m/f/d)
BITControl develops intelligent software solutions for water and wastewater technology as well as for biogas plants. Its particular strength lies in the combination of [...]
Electrical engineering planner wanted
We are hiring: Electrical technician / electrical engineer / master electrician (m/f/d) with professional experience. BITControl is a specialist planner for electrical, mechanical and process engineering for wastewater treatment [...]