Optimisation of the sludge cycle

structure-square

Improving the purification performance of the Zahmen wastewater treatment plant

Since its construction, the Zahmen wastewater treatment plant in the municipality of Grebenhain has had problems with the function of the secondary clarifier. Here, the sludge level rose significantly to critical levels when the mixed water inflow began and continued.

The wastewater treatment plant was analysed, recalculated and evaluated by BITControl. The following measures were implemented to improve the treatment performance:

  • A new, larger inlet cylinder with inlet pipe was installed in the secondary clarifier
  • A partition wall was installed in the RLS shaft in order to be able to control the two secondary clarifiers separately. A bypass pipe was also installed to improve the operating point of the pumps.
  • At the same time, parts of the EI&C technology were renewed or supplemented: switchgear, sludge level measurement, automation technology
    The return sludge control was converted to sludge level control.
Further contributions

News from BITControl

Company holidays, Christmas greetings
Company holidays We are taking a company holiday over the turn of the year from Monday, 23 December 2024 up to and including 3 January 2025. Well recovered and full of [...]
AQUA DESIGNER Webinar
AQUA DESIGNER is the practice-orientated design software for activated sludge plants. AQUA DESIGNER is programmed experience: because it incorporates over 25 years of planning experience [...]
Arabic-Kurdish lunch
Today we had Arabic-Kurdish food and everyone loved the hummus, kibbeh, zaalouk, kabseh and salad fattoush. Many thanks to [...]