Optimisation of the secondary clarifier at Kaisersesch wastewater treatment plant

structure-square

Partial renewal of the mechanical equipment

The Kaisersesch wastewater treatment plant with a capacity of 5,500 PE is a mechanical biological wastewater treatment plant with simultaneous aerobic sludge stabilisation. The biological stage is designed as a combined tank.

The aim was to improve the discharge values by reducing the flow velocity. To this end, the geometry of the central structure was adapted, for example by adding a ring-shaped baffle with a base plate. Parts of the mechanical equipment were also replaced.

During the conversion work, the NKB was taken out of operation and the biology system was temporarily operated as an impoundment.

Further contributions

News from BITControl

Company holidays, Christmas greetings
Company holidays We will be closed for the holidays from Monday, 22 December 2025 through 2 January 2026. In the new year, we will be open from [...]
AQUA DESIGNER - Dimensioning of wastewater treatment plants
Dimensioning software - almost 30 years of programmed experience 29 years ago, we launched AQUA DESIGNER, the software for planning [...]
Pumping, hiking, AI and good food
BITControl company outing on 12 and 13 September 2025 This year's two-day company outing took us to the Bonn/Königswinter region and offered a [...]