30.04.2019

Modernisation of the Beilingen wastewater treatment plant

structure-square

The sewage treatment plant Beilingen, VG Speicher is designed for 2,650 PE. Approx. 1,900 PE are connected.

Together with the operator, BITControl identified and implemented the following measures for the modernisation and energy and process optimisation of the wastewater treatment plant:

  • Replacement of the old spiral aerators with a new aeration system with separate circulation and aeration, installation of submersible motorised agitator and positive displacement blower
  • Installation of a baffle with base plate and baffle plate in the secondary clarifier
  • Renewal of the switchgear with frequency converters
  • Modernisation of the measurement and control technology for optimised operation of the wastewater treatment plant: level measurement, oxygen, nitrate, pH and sludge level measurement, automation and PLC programming
Further contributions

News from BITControl

Our new company brochure is here!
Three areas of expertise. One shared goal. Process engineering, specialist planning and software work together seamlessly at BITControl. This results in bespoke solutions for water, [...]
Lunch together by the lake and in the garden
In April, we were treated to a very special lunch: the Maximinschule – a special school for learning and language – [...]
BITControl is a FlowChief partner
BITControl FlowChief has been a Silver Certified Partner since February 2026. Service is the be-all and end-all. Service is our top priority [...]